Friday, 30 December 2011
Tiling
As with the rest of the building we've kept things simple with clean white tiles for the food prep' and washroom areas. The photo shows what progress had been made when we were last on site, and judging by the speed at which they were working, Mike and his team from DJBennett & Son should have completed their work before the holiday.
And with the kitchen fitters due to start installing equipment into this area immediately after New Year it should soon be transformed into a completed Cafe/Kitchen.
Tuesday, 27 December 2011
Thursday, 22 December 2011
Wrapped up
Everything is still going to schedule so the New Year should see a busy January leading to handover of the completed building in February. Meanwhile all manner of finishes, fixtures and fittings are now starting to arrive and are being installed. This includes the servery, which will provide the focal point in the Cafe. Unfortunately we'll have to wait until well past Christmas before we can unwrap it, but we're sure it'll be well worth it.
Tuesday, 20 December 2011
Inside curve
Wednesday, 14 December 2011
Emerging
Porcelain
It's getting extremely busy on site with various trades now working around each other as the finishes start to be installed.
Part of this is the second fix of the plumbing, with the installation of sinks, WCs and their associated taps etc. So far one of the basins has been installed but that's sure to change over the next few days with all these ready to be unpacked and fixed in place.
Saturday, 3 December 2011
Heating
Installation of the bulk of the underfloor heating pipework happened a few weeks ago when the floor screed was poured. The plumbers are now installing all the other pipework that connects the gas fired boilers to the heating system.
Once the pipework system is complete and pressure tested they will then be able to fire up the boilers, allowing the heating system to start the important process of drying out the building.
Monday, 28 November 2011
Cladding
The third and final main external finish is now being applied to the building. After the standing seam Aluzinc and the addition of the ivory render last month, we now have timber cladding being installed to complete the facade.
Sourced locally from South Wales, the Larch timber is not only a sustainable material but also a locally grown one. Western Red Cedar was considered early in the design but this was ruled out as it would have to have been shipped in from Canada, with a significantly larger carbon footprint than the Larch.
Tuesday, 15 November 2011
Busy busy...
The other major 'wet' trade on site now are the plasterers, who are starting to cover up the blockwork and give the walls their final smooth finish. All in all it's a busy site and despite the extensive scaffolding it's getting easier to visualise what the building will be like when it's complete.
Sunday, 23 October 2011
Render
Barn Dance
Wednesday, 19 October 2011
First Fix
This space will be partitioned off into offices and a meeting room.
Saturday, 8 October 2011
Chasing
Okay, so it's not the most exciting photo. But after mentioning in the previous blog that other trades would be starting soon we thought you might like to see that the electricians are now on site.
In order for the Electricians to do their 'first-fix', when they install the backboxes for the electrical sockets and the conduit through which they run the electrical cables, they have to 'chase' the walls. This involves the unenviable task of cutting channels in the blockwork to agreed socket locations - in this case it's for sockets within the Cafe area. Once they've done this they can install the backboxes and the conduit, before the plastering starts.
Tuesday, 4 October 2011
Glazing
So with our unexpected late summer weather over, and autumn returning, it's great to be able to report that much of the final roof covering is now installed along with the first of the windows. The photo below shows the roof of the preschool, with the bulk of the external roof cladding inplace and the skylight opening formed ready for the glazing. If you look very closely at the righthand side of the photo you'll see that the windows for the offices have just been installed.
The rest of the glazing will be installed over the next few weeks, helping to make the building weathertight and allow other trades to start work inside.
Monday, 19 September 2011
Another dance
Saturday, 10 September 2011
Standing seam
While the mass of scaffolding on site obscures the view of some of this work the photo below shows that installation of the roof is well underway and judging by the rapid progress it won't be long before this is complete.
Saturday, 20 August 2011
Holiday?
Wednesday, 3 August 2011
More photos
Friday, 15 July 2011
Wednesday, 6 July 2011
Rainwater
We have endeavoured to make the new building as sustainable as possible, with one particular area being the inclusion of a rainwater harvesting system. This system will collect rainwater off the roof the building and reuse it for use flushing WCs and irrigating the external landscaping. So it's good to see that the rainwater harvesting tank has arrived on site, ready to be installed below ground as part of the groundworks.
Time for a cuppa?
Monday, 27 June 2011
Ground Breaking
This morning saw almost 30 members of Resound Church and local Councillors don Hi-Vis vests and hard hats to join the Cowlin site team for the Ground Breaking ceremony to celebrate that construction is finally underway.
Tim Groves, Ruth McConnell and Joyce Lewis did their bit with with the shiny spades before we raised a glass of celebratory bucks fizz and handed the site back to the Cowlin team to get on with the real work.
Wednesday, 22 June 2011
Progress Photo No.2
Next week we'll have a ground breaking ceremony to celebrate the start of the work on site and will be raising the profile of the project via the local press - so look out for photos of Tim with a shiny spade!
Wednesday, 8 June 2011
Progress Photo No.1
Sunday, 5 June 2011
The begining
BCF is a network of three churches in the Bristol area, all joined together by a shared history, common values, and a commitment to enriching the lives of local residents.
Over the past forty years BCF has developed strong links with the communities of Emerson’s Green and surrounding areas within Bristol.
Building on this, we are now redeveloping the site that used to house one of our old church building in Blackhorse Road, Mangotsfield. In desparate need of repair, the old building would have struggled to meet our current and future needs even if we had been able to adequately refurbish it. So we decided to develop the new building, Resound. With intelligent design and a commitment towards environmentally sustainable construction, the building will prove visually stimulating and resource efficient.
As a replacement building it will enable BCF to deliver on its many commitments and ambitions. Particularly the centre will be home to Resound Church, the established Crossways pre-school, and a new community centre for the locality. We hope that Resound will not only become a meeting ground for our church members, but also the familes who use Crossways pre-school, along with the residents of Mangotsfield and Emersons Green.
Construction starts tomorrow 6th June 2011, with the completed building due to be open in February 2012.
Sunday, 8 May 2011
D Day
Site work is due to start on 6th June with the new building completed and ready for us to use in February 2012!
We'll be posting images of the build once it starts along with more regular updates on progress on the blog, so watch this space.
Tuesday, 5 April 2011
Planning Part 2
Whilst these are all minor changes, and ones that most people won't notice, planning law dictates that we have to get them approved before we can be sure of the resultant financial savings. Today we received the good news that the amendments have been approved.
We also received the final Contract at the weekend and are now reviewing it prior to getting it signed. So expect us to be advising when the Contractor will start on site very soon.
Monday, 14 March 2011
Chairs
However we've not just been thinking about seating, we've also been busy finalising the contract with the builder in parallel with arranging the necessary funding via our preferred ethical bank Triodos.
Sunday, 13 February 2011
Dancing the night away
We'd like to say a big thankyou to everybody who came along and supported the project, especially Sarah H and Nikki M who organised the Barn dance and the Raffle.
We're all looking forward to the next event!
Thursday, 6 January 2011
One
Although we're not quite ready to place a contract with our preferred Contractor we have given them a Letter of Commitment which will enable them to continue with Value Engineering. It's important that this is completed as thoroughly as possible to give us the best possible price before we move forward with developing the detail design and starting construction on site.
If this last statement makes you think site work is still some distance away, it's worth pointing out that the benefit of the 'Design and Build' approach that we have taken is that the Contractor will be progressing design of some elements of the building while constructing others. For example, it is normal to be casting foundations and erecting steelwork while the design of the electrical systems is still being completed as these don't impact one another.