December has arrived along with the first frost of the winter and while the building isn't yet protected by a functioning heating system, the plumbers are making good progress.

Installation of the bulk of the underfloor heating pipework happened a few weeks ago when the floor screed was poured. The plumbers are now installing all the other pipework that connects the gas fired boilers to the heating system.

Once the pipework system is complete and pressure tested they will then be able to fire up the boilers, allowing the heating system to start the important process of drying out the building.